Plans unveiled for upgrades to A47
Highways England has announced its preferred routes for dualling three parts of the 115 mile stretch of the A47 between Peterborough and Great Yarmouth following a public consultation.
Around Norwich, work includes dualling of the A47 between North Tuddenham and Easton, further east, between Blofield and North Burlingham, along with junction improvements at the Thickthorn Interchange with the A11 plus two busy junctions in Great Yarmouth, on what was formerly the A12.
Further west at Peterborough, the work involves dualling a busy stretch between Wansford (A1) and Sutton, and improving the Guyhirn junction with the A141.
Below is the full list of the projects
A47 North Tuddenham and Easton: Option 2 was chosen for the dualling between North Tuddenham and Easton, which will see the A47 upgraded to dual carriageway along its existing route, with the alignment been amended to address some of the key concerns raised.
A47 Blofield to North Burlingham: For the Blofield to North Burlingham dualling, option 4 was selected which will see a new stretch of dual carriageway built a little to the south of the existing A47.
A47 Thickthorn Interchange with A11: The consultation was about a single option for the junction improvements, which will now see delivered a direct link from the A11 northbound to the A47 eastbound, and similarly from the A47 westbound to the A11 southbound, alleviating congestion at the roundabout.
A47 Great Yarmouth junctions (formerly A12) At Great Yarmouth, the Vauxhall roundabout will be enlarged and fully signalled, and get an extended bridge and a new slip road. There will also be minor improvements at the Station Approach junction, while the Gapton roundabout will be significantly improved as it is widened and fully signalled too.
A47 Wansford to Sutton: Option 2 was chosen for dualling the A47 between the A1 junction at Wansford and the dual carriageway section west of Peterborough. This will include building a new dual carriageway to the north, at the western end, and to the south, at the eastern end. There will also be a dedicated slip road from the A1 southbound to the A47 eastbound to alleviate congestion at the junction. Since the consultation, the alignment has been amended to address some of the key concerns raised
A47 Guyhirn: The single option proposed for the Guyhirn junction will see the roundabout enlarged and the road over the River Nene Bridge widened to three lanes to ease congestion.
Subject to statutory processes, work on the six projects could begin as early as March 2020, with completion dates starting from March 2021.